海外新闻

Primus Line 为布里斯班历史悠久的主干线注入新活力

发布人:CSTT 2021-09-07
布里斯班最古老和最重要的饮用水管道之一位于纽斯特德和毅力谷繁华的商业和夜生活区的安街下。

今年早些时候,Urban Utilities 在这条拥有 130 年历史的管道上完成了一项耗资数百万美元的修复项目。

通过使用非开挖技术 Primus Line®,该项目有望将管道的使用寿命延长至少 50 年,提供一种对交通和附近企业和居民影响最小的经济解决方案。
安街管道是一条水泥衬里的铸铁管道,向市中心和内城郊区供水。
在早晚高峰消费时段,每秒约有 500 升水流经管道。

每天有数千辆汽车沿着四车道公路行驶,这条公路是布里斯班中央商务区最繁忙的公路之一,交通路线上遍布企业和巴士站。

在严重拥挤的城市环境中更换水管可能是一个代价高昂且具有破坏性的过程,因此在这种情况下,非开挖技术是成功的关键。

考虑到管道的位置,选择 Primus Line 是因为它可以穿过管道中的几个弯道,并使用几个小工作井进行安装,以尽量减少对交通的影响。

Primus Line breathes new life into historic trunk main in Brisbane



One of Brisbane’s oldest and most important drinking water pipes runs under Ann Street in the bustling business and nightlife district of Newstead and Fortitude Valley.

Earlier this year, Urban Utilities completed a multi-million-dollar rehabilitation project on this 130-year-old pipeline.

With the use of the trenchless technology Primus Line®, the project is expected to extend the life of the pipeline by at least 50 years, providing an economical solution with minimal impacts to traffic and nearby businesses and residents. 

The Ann Street pipeline is a cement-lined, cast iron pipe, and helps to supply water to the city centre and the inner-city suburbs.

During the morning and evening peak consumption periods, about 500 L of water per second flows through the pipe. 

Thousands of vehicles a day roll along the four-lane road, which is one of the busiest roads in Brisbane’s central business district, and businesses and bus stops line the traffic route.
 
Replacing water mains in heavily congested urban environments can be a costly and disruptive process, so in this case trenchless technology was the key to success.

Given the location of the pipe, Primus Line was chosen as it could pass through several bends in the pipe and be installed using a few small pits, to minimise the impact on traffic. 

Planning 

As Primus Line is a flexible stand-alone pipeline, which is installed with an annulus gap, it can withstand the operating pressures of the water main, but not the external loads from the traffic on the road above. 

The project at Ann Street was preceded by a detailed condition assessment of the host pipe and economic evaluation in order to ensure the existing pipeline could withstand external loads in the future.

The results showed that the pipeline had sufficient load bearing capacity to allow the use of a semi-structural lining system such as Primus Line for the desired service life of at least 50 years. 

The perfect choice 

Due to its unique three-layer structure, the Primus Liner combines flexibility with extremely high material strength.

As a self-supporting pressure pipe liner independent of the old pipe, it absorbs the entire operating pressure, while the old pipe merely functions as a conduit. 

In accordance with ISO 11295, Primus Line is an independent pressure pipe liner capable on its own of resisting without failure all internal loads throughout its design life.

It has the ability to negotiate bends of up to 45 degrees, allows for seasonal movement of the pipeline and ensures the required operating pressure of up to 11.3 bar. 

Despite the reduction in cross-section of the DN 600 pipe, flow calculations showed the client that the installation of a Primus Line DN 500, with its low friction coefficient of only 0.028, would still provide the required flow. 

Before the start of the project, a large- scale trial with a length of 350 m was carried out with the Primus Line system – developed and produced in Germany.

In a single day, the pre-folded liner was pulled into the 350 m field trial section of the Ann Street trunk main, formed into its circular shape with compressed air and successfully connected to the pipeline network.

Start of the major project 

The successful completion of the trial allowed for the commencement of the Ann Street project, where detailed design and construction planning was performed in 2019 by Urban Utilities.



Small excavations are
sufficient for the installation.

The initial stages of the project also involved cleaning and prepping the existing pipe to make it suitable for installing the liner, while the installation phase began in mid-2020 and was completed in early 2021. 

Most of the work took place at night and the small construction pits were closed during the day with large steel plates, to allow traffic to continue to flow.

The entire project was carried out by Urban Utilities’ own workforce, and the company had previously installed Primus Line on other rehabilitation projects in its service region. 

Urban Utilities had engaged Primus Line to provide training to its team, and kept the required necessary tools and spare parts in stock to perform Primus Line installations and possible repairs and maintenance in-house.
 
The Primus Line team provided engineering support and accompanied the beginning of the measure with a supervisor.

Four installation sections were necessary to rehabilitate the 2.2 km long pipeline section, with the Primus Line system DN 500 PN 16 used to rehabilitate the DN 600 water pipeline.

Primus Line delivered the four liner sections pre-folded in a U-shape and wound onto drums.

The liner insertion into the old pipe was done with a winch and in the process passed through some additional smaller intermedia pits to reinstate valves and offtakes.

The liner was pulled through these pits and cut afterwards to install the Primus Line connectors and the necessary valves and t-pieces. 

Special DN 500 connectors with a DN 600 flange were used to ensure the connection to the flange on the host pipe while keeping the pits as small as possible. 

A pressure test concluded the successful installation before the main was disinfected and returned to operation.

凡本网的所有原创作品版权均属于《非开挖技术信息网》,转载必须保证作品的完整性并注明来源。转载作品与网友言论 不代表非《开挖技术信息网》观点。
©2010 All rights reserved 版权所有 © 上海科熙文化交流有限公司
中国地质学会非开挖技术专业委员会(CSTT)
技术支持:上海攸攸网络